Major Construction in Precinct

 

Projects – Construction Start and End Dates*

Projects
Construction Starts
Completed by:
Brisbane Metro Early/Mid 2020 Operational by 2023
Neville Bonner Bridge Early 2020 Opening late 2022
New Performing Arts Venue Early works from early 2020 Opening late 2022
Riverside Open Space Started Opening early 2021
Cross River Rail Early works started Operational 2024
Queen’s Wharf Development Works has started Open 2022

* subject to change