Precinct Construction Update
September 19, 2024 – Community
Construction projects continue throughout the precinct.
New Performing Arts Venue (NPAV)
- The NPAV glass façade is taking shape extending along both Russell St and Grey St and spanning two stories. For further project updates – Click here
Brisbane Metro
- Brisbane Metro construction activities are continuing in South Bank at Cultural
Centre station. Brisbane Metro will start operating from October between
Eight Miles Plain and UQ. Services through South Brisbane are expected to commence Nov/Dec 2024. For further project updates – Click here
Cross River Rail
Cross River Rail construction works are continuing throughout the precinct at Roma St, Albert St and Woolloongabba Stations. Below surface works remain ongoing at all stations. Works continuing on Albert St between Elizabeth St and Charlotte St for construction of the Green Spine. For further project updates – Click here